Green grass and erosion controls on SB-1 Cell No. 2.


EPA and FMC perform Community Outreach at the Front Royal Annual Festival of Leaves.

EPA Oversight Contractor inspects the Geosynthetic liner installation.

Installing Geosynthetic liner on SB-1 Cell No. 4.

Screening rocks from the soil before the soil is placed on SB-1 Cell No. 4.

Rolling the soil so it is smooth before deploying Geosynthetic liner.