Recent Site Activities (December 2010)


Collecting soil samples at the Emergency Lagoon berm.

Grading the south side of the Former Plant Area.

The new berm road between the Shenandoah River and Sulfate Basin No. 2.

Performing Pre-Design field studies at Operable Unit No. 7.


Removing a section of sewer from the Former Plant Area.

Using a backhoe to expose soil for sampling at the Emergency Lagoon.