Recent Site Activities (July 2008)

Benching
Benching the slope on the west side of viscose basin 6.
EPA
EPA full time on site oversight contractor inspects the leachage conveyance system at viscose basins 4 - 6.
Installing
Installing a leachate conveyance system around viscose basins 4 - 6.
New leachate
New leachate conveyance system manhole.
Preparing
Preparing the cover soil on viscose basins 4 - 6 before placing plastic liner on top.
Receiving
Receiving imported soil to be used on the cover of viscose basins 4 - 6.